Overview  |  Markets  |  Showcase Projects  |  Panel Fabrication

Showcase Projects

Commercial
Amgen Building
Bank of America, Data Center
Northrop Critical Power Supply

Industrial
Hyperion C-741
Hyperion Dice 1
Port of LA Berths

Institutional
Central Jail
LA Convention Center
Oakland Arena
Oakland Coliseum
Rancho Los Amigos - Facility Operations
Rancho Los Amigos - Hospital

Transportation
Metro Redline Station
Metro Redline Station B221
Metro Redline Tunnels B251, B, C and D
Metro Redline Tunnels B251 E and F
San Joaquin Hills Transportation Center
Denver I-25
Metro Gold Line
ATSAC - Highland Park
CCTV - Cal-Trans Route 73

Showcase Projects
Hyperion C-741
Los Angeles, California

Owner:

City of Los Angeles

Architect:

Daniel J. Mann, Johnson and Mendenhall/Black & Veatch

Engineer:

Daniel J. Mann, Johnson and Mendenhall/Black & Veatch

General Contractor:

Dillingham/Ray Wilson Joint Venture

Project Duration:

60 Months

Contract Amount:

$13,000,000

Project Description:
The City of Los Angeles Hyperion Sewage Treatment Plant in Playa Del Rey, project C-741 added 20 new digesters that will have a total holding capacity in excess of 50 million gallons of sewage, with a processing rate of 8,000 gallons per minute. Besides the twenty new digesters, Dynalectric furnished and installed eight 15KV substations, two 35KV transformers, walk-in load centers, numerous sections of motor control and all required instrumentation.

Due to a high groundwater table and visual consideration, this complex of modified "egg" shaped digesters is the largest in the United States.